BHP Group (ASX: BHP) plans to double copper production from its South Australian operations to about 500,000 tonnes a year by 2035 and up to 650,000 tonnes a year by 2040, the company told investors at the start of a two-day site tour on 23 November 2026.

The plan, set out in a presentation titled “Copper South Australia: Unlocking a world-class copper province”, covers the Olympic Dam, Carrapateena and Prominent Hill mines. Including gold, uranium and silver by-products, BHP is targeting about 800,000 tonnes of copper equivalent a year by 2035 and about 1 million tonnes by 2040.

Reuters reported the program would cost US$14.2 billion to US$18.1 billion. BHP’s own presentation breaks out Phase 1 capital spending of US$5.8 billion to US$7.5 billion for mines and concentrators, and US$3.2 billion to US$4.1 billion for the smelter and refinery expansion.

The targets and the returns BHP expects

Phase 1, which takes production to about 500,000 tonnes of copper a year by 2035, carries an indicative internal rate of return of 14 to 17 percent and capital intensity of US$18,000 to US$23,000 per tonne of copper equivalent, according to the presentation.

BHP expects Copper South Australia to generate about one third of its copper growth to 2035, and says its copper business can fund the growth spending from operating cash flow. Geraldine Slattery, BHP’s head of Australian operations, told investors on the tour: “We start from a strong position as the world’s largest copper producer, with a sector-leading growth pathway that can be funded from existing copper cash flows.” BHP shares rose 2.18 percent to A$52.52 on 23 November 2026, the day the tour material was released.

Two technologies carry the plan

Block caving is a bulk underground mining method in which ore is undercut and allowed to collapse under its own weight. BHP says it structurally lowers mining costs and allows more automation, and Olympic Dam mine production would rise from about 11 million tonnes a year now to about 21 million tonnes a year after the ramp-up.

Two-stage smelting matters because of Olympic Dam’s mineralogy. As mining moves into the southern part of the deposit, the copper-to-sulphur ratio falls below the range a single-stage smelter handles economically. The expansion adds a new primary flash smelting furnace and acid plant, converts the existing direct-to-blister furnace into a secondary flash converting furnace, and expands the refinery.

The resource behind the plan is not a reserve

The ambition follows a resource update BHP disclosed on 20 October 2026 in its operational review for the quarter ended 30 September 2026. The first block-cave Mineral Resource at Olympic Dam stands at 10,730 million tonnes grading 0.59 percent copper, 0.19 kilograms per tonne of uranium oxide (U3O8), 0.21 grams per tonne of gold and 1 gram per tonne of silver. The existing sub-level open stoping resource is 1,590 million tonnes at 1.56 percent copper, and together the classified underground resource is estimated to contain 88.1 million tonnes of copper, 2.8 million tonnes of U3O8, 103 million ounces of gold and 498 million ounces of silver.

Those are contained-metal figures, not recoverable production, and the distinction matters. The block-cave resource has not been converted into an Ore Reserve, and BHP says its development timeframe is not yet known. The estimate also assumes the higher-grade stoping resource is mined first. The 10.73 billion tonne headline is a geological option, not a mine plan.

Where the money goes, and when decisions fall

Phase 1 is a set of integrated projects rather than a single build. Carrapateena Expansion, which adds a block cave about 450 metres below the existing sub-level cave, carries capital spending of US$1.8 billion to US$2.1 billion, with a final investment decision in the first half of 2028.

The Olympic Dam Mine and Concentrator Growth project is the largest single piece. Its 11 million tonne a year stoping operation continues at a 1.9 percent copper head grade, while a hydromet expansion lifts uranium processing capacity by about 50 percent. Capital spending is US$4.1 billion to US$5.4 billion, with a final investment decision in calendar 2029 and first production in the 2034 financial year.

The smelter and refinery expansion is the first major decision. Its final investment decision is scheduled for the second half of calendar 2027, with first production in the 2032 financial year.

By-products do much of the economic work

Copper South Australia recorded by-product revenue of US$2.3 billion in the 2026 financial year, alongside record earnings before interest, tax, depreciation and amortisation of US$3.2 billion. By 2035, BHP expects by-product output to rise about 50 percent to 300,000 tonnes of copper equivalent a year: gold up 45 percent to more than 570,000 troy ounces a year, uranium up 65 percent to about 6,000 tonnes a year, and silver up 40 percent to more than 2.8 million troy ounces a year.

That stream is why the smelter matters commercially as well as technically. Olympic Dam ore carries radionuclides that require on-site smelting, and processing on site captures more of the uranium, gold and silver value.

The next milestone is the smelter decision in the second half of 2027. Until then, the 650,000 tonne target is a strategy backed by a resource and a staged capital plan, not a sanctioned build. BHP has shelved South Australian expansion plans twice before, in earlier decades, when costs rose and commodity markets turned. The test this time is whether the first decision lands on schedule.